# Delivery health

Earned value across the portfolio — cost and schedule performance per project, the S-curve behind one of them, and what the open risk register would cost.

![Delivery health](https://projectri.com/docs-shots/workspace-reports-delivery.png)

## What it is

Delivery health is the portfolio read before the meeting. It plots every
baselined project on cost performance against schedule performance, draws the
weekly planned-versus-earned-versus-actual curve behind any one of them, and
sums the open risk register into what it would cost if those risks land. The two
halves are on one screen because they are the two halves of the same sentence in
the same conversation.

## How to get there

**Delivery health** sits under Reports in the main navigation, gated on
`report.view`. There is no plan gate.

Inside, the panes are gated separately, and a pane you may not have is absent
rather than leading to a refusal:

- **Quadrant** and **S-curve** need `report.view`.
- **Risk exposure** needs `risk.view`.
- `report.cost` decides whether any money is shown at all. Without it the cost
  figures are *missing* from the payload rather than blanked.

With neither key the page says so plainly rather than opening empty.

## How to use it

### Read the quadrant

1. The tiles across the top are **Measured** (projects with a baseline, out of
   the active portfolio), **At risk**, **Over cost**, **Behind schedule** and,
   with cost permission, **Forecast variance** — budget less forecast at
   completion, where negative is an overrun.
2. The plot puts schedule performance on one axis and cost performance on the
   other, with reference lines at 1.0. The bottom-left corner is the meeting
   agenda. Axes are clamped between 0.5 and 1.5, so one disastrous project does
   not rescale the plot until every healthy one sits on the line.
3. Below it, one row per project with **Complete**, **Planned**, **Against
   plan** in points, **SPI** and — with cost permission — **CPI**, **Budget**,
   **Spent** and **Forecast variance**, plus a sentence reading the numbers out.
4. Each row states which percent-complete method it uses: milestone-weighted by
   billed value, effort as hours logged against hours estimated, or the project
   manager's own judgement per task.
5. **Not measured** at the bottom names the projects that have no baseline. They
   are named rather than dropped — a portfolio screen that silently omits the
   unbaselined projects omits exactly the ones nobody is managing. When one
   reason covers the whole list it is said once, and the list becomes names.

### Read one project's S-curve

1. Press **S-curve** on a project row, or open the **S-curve** tab and pick a
   project.
2. The chart is that project's weekly snapshots since it was baselined —
   **Planned value**, **Earned value** and **Actual cost**.
3. Without cost permission it degrades to a single progress line rather than
   three currency lines flat along zero.
4. A project with one week of history has no curve yet; the snapshot runs
   weekly, so the line appears once there are two. The figures above it are
   current either way.
5. If the percent-complete method changed part-way through the history, the
   chart says so — a step in the line may be a change of ruler rather than of
   progress.

### Read the risk exposure

1. Open **Risk exposure**. Scope it to the whole portfolio or to one project.
2. The tiles are **Gross exposure** (what it costs if every open risk lands at
   once), **Weighted exposure** (the same weighted by probability — the number
   to hold a contingency against), **Open risks**, **High risks** (probability
   times impact of 15 or more on the five-by-five matrix) and **Weighted days at
   risk**.
3. **Top risks** lists the ten highest-scoring open risks with their score,
   band, weighted cost and a link to the project. The totals above are summed
   over *every* open risk, so these ten rows will not add up to them.
4. Only risks that are open, mitigating or accepted count. A closed risk costs
   nothing.

## What it affects

- **Nothing here is editable.** Earned value is computed and a risk register is
  edited beside the person who raised it.
- **A project has to be baselined to appear.** Freezing the current plan on a
  project brings it into the measured set from the next snapshot.
- **The snapshot is weekly.** The curve is a stored history, so a project's line
  grows one point a week rather than being recomputed from scratch.
- **The quadrant verdict comes from the server**, not from the numbers on
  screen. A reader without cost permission has no CPI, and re-deriving the
  verdict locally would turn "over cost" into "no data" for the whole
  portfolio.
- **Delivery performance and Risk exposure are both schedulable.** Both appear
  as built-in reports in
  [scheduled delivery](/docs/workspace/reports-schedules), and a scheduled copy
  runs the same engine as this screen with the recipient's own permissions.

## On mobile

**Delivery health** in the app has the same three panes, minus the scatter plot
— a quadrant needs a plane and gets a ranked list instead. It reads the same
payload and applies the same cost rule, so the S-curve degrades to a progress
line for a cost-blind reader there too. Nothing on the phone is editable.

## Limits and gotchas

- **A baseline taken before planned costs were recorded** falls back to the
  project budget as its budget at completion, and the row says so. Re-baseline
  to cost the plan.
- **Money needs a reporting currency.** If the risk register carries a cost
  impact but the workspace has never set a reporting currency, the exposure
  figure cannot be shown as money. It appears once any invoice, expense or time
  entry is priced.
- **Cost fields are absent, not zero.** A reader without `report.cost` gets rows
  with the money keys missing, which is why a cost column simply is not there
  rather than showing dashes.
- **A failed load says so and offers a retry** rather than sitting on its
  skeleton, which used to make an expired session look like a slow portfolio.

## Related

- [Reports](/docs/workspace/reports) — the delivery figures without the earned-value frame.
- [Portfolio](/docs/workspace/portfolio) — the projects and clients being measured here.
- [Revenue](/docs/workspace/reports-revenue) — earned against contracted, on the money side.
- [Scheduled delivery](/docs/workspace/reports-schedules) — having this arrive weekly instead.

## Related

- [Reports](https://projectri.com/docs/workspace/reports.md): The fixed report page — completion, throughput, burndown, team performance and the effort figures, for this week, this sprint, this month or all time.
- [Portfolio](https://projectri.com/docs/workspace/portfolio.md): Every project on one timeline, in swimlanes by client or department, with milestones, active sprints and what is running late.
- [Revenue](https://projectri.com/docs/workspace/reports-revenue.md): What has been earned against each contract, and what was billed for the work behind it — recognition and realization on one screen.
- [Scheduled delivery](https://projectri.com/docs/workspace/reports-schedules.md): Reports that arrive on their own — the cadence, the recipients, and whether the ones you thought were arriving still are.